SUGAR DEVELOPMENT CORPORATION v CONSTRUCTION ENGINEERS AND BUILDERS LTD 1986 TLR 172 (CA)
Court Court of Appeal of Tanzania - Dar Es Salaam
Judge Mustafa JJA, Makame JJA, Omar JJA
H
CIVIL APPEAL 3 OF 1986
Flynote
I Contract - Building Contract - Construction of "repetition of default" - Whether
repetition of a default can have exclusive reference to the date of its first occurrence.
1986 TLR p173
-Headnote
A The appellant, SUDECO, contracted with the respondents, Builders, for the latter
to erect a multistorey building for SUDECO in Dar es Salaam. After proceeding with
the works for sometime the respondent Builders defaulted. In terms of Clause
25(1)(b) of the Agreement the Architect served notice of default on the Builders on
7.6.82 on the ground of the B Builders' "failure to proceed regularly and diligently
with the works". On 26th January, 1983 the Architect found that such default was
repeated and on 4.2.83 notice was served on the Builders terminating the contract. In
April, 1983 the appellant engaged another contractor to erect the building.
C The Builders sued SUDECO for breach of contract. The matter was, in terms of
the arbitration clause in the Agreement, eventually referred to an arbitrator who
found in favour of SUDECO. On appeal to the High Court it was held that the notice
of termination by the appellant, SUDECO, was invalid on the ground that there was
no evidence that a repetition of the default had occurred within 10 days when the
notice of termination was given. The High Court D reversed the decision of the
arbitrator.
On further appeal to the Court of Appeal of Tanzania it was argued for the Builders
that there was no evidence that the notice of termination of 4.2.83 was made within
10 days of the repetition of the default. It was not established that the E default
discovered on 26th January, 1983 was repeated the first time that day.
Held: (i) a repetition of a default can have no exclusive reference to the date of its first
occurrence, it is repeated every time the default occurs; F
(ii) the repetition of a default is the act of the default itself being repeated, and
once the default is repeated, then notice of termination within 10 days of such
occurrence complies with the provisions of clause 25(1)(b);
(iii) the notice of termination given on 4.2.83 was within 10 days of the
repetition of default on 26.1.83, and that was in terms of clause 25(1)(b) of the
Agreement. G
Case Information
Order accordingly. H
No case referred to.
T. L. Mkude, for the appellant
M.A. Lakha, for the respondent I
1986 TLR p174
MUSTAFA JA
[zJDz]Judgment
A Mustafa, J.A.: The appellant (Sugar Development Corporation, hereinafter called
the Corporation) had entered into an agreement with the respondent (Construction
Engineers and Builders Limited, hereinafter called the Builders) for the Builders to
erect a multistorey building for the Corporation in Dar es Salaam. The Agreement
(hereinafter called the B Agreement) was dated 19.9.80, the contractual sum was
about 33.5 million shillings, the completion date was 3.1.83, the time for completion
was 120 weeks, from 15.9.80 to 3.1.83. Shortly after the Builders had commenced
building a variation of the Agreement was made between the Corporation and the
Builders by which additional storeys were to be C added to the original building and
the price was increased to about 52.7 million shillings and the completion date was
extended to 3.7.84. The Agreement was on the lines of the usual Royal Institute of
British Architects (R.I.B.A) form of contract.
D In terms of clause 25 (1) (b) of the Agreement the Architect served notice of
default on the Builders on 7.6.82 on the ground of the Builders "failure to proceed
regularly and diligently with the works". In January, 1983 the Architect found that
such default was repeated and on 4.2.83 notice was served on the Builders
terminating the contract. In April, 1983 E the Corporation employed another
contractor to erect the Building.
The Builders filed a suit in the High Court for breach of contract, and the matter was,
in terms of the arbitration clause in the Agreement, eventually referred to a single
arbitrator, Mr. A.G.I. Shayo, then President, Institute of Engineers, F Tanzania, for
arbitration.
The Arbitrator heard evidence and made his award. The Arbitrator found in favor of
the Corporation and the Builders appealed to the High Court alleging misconduct on
the part of the Arbitrator and asking for the award to be set aside. G The High Court
(Mapigano, J.) held that the notice of termination by the Corporation was invalid and
that the Arbitrator had misconducted himself. The judge, apart from remitting the
amount claimed for compensation to the Arbitrator for a fresh hearing, in effect set
aside the award. From that Ruling the Corporation has appealed to this Court. H
In his award the Arbitrator made a number of findings. The main ones were:
(1) The Builders' responsibility was limited to the scope of works as
defined in the original Agreement of 19.9.80 including any I variations that were
issued but did not extend to the overall
1986 TLR p175
MUSTAFA JA
A increased scope of work. The sum involved would be Shs. 33.54
million less Shs. 8.04 million for supplies and sub-contracts, i.e. Shs.25.5 million only.
(2) The Architect's notice of default dated 7.6.82 was valid.
(3) That there was an element of negligence on the part of the Architect in
dealing with applications for extension of time by the Builders. B
(4) The notice of termination of 4.2.83 issued by the Corporation to the
Builders was in conformity with the Agreement and was valid.
(5) In view of the finding that the termination was valid there was no
point in considering the issue of extension of time. C
(6) The Builders to compensate the Corporation as follows:
(i) extra cost of completing works 38,384,558.45
(ii) extra cost of consultant's fee 3,294,409.30 D
41,678,967.75
(7) The Corporation to return to the Builders the equipment and tools in
good condition, fair wear and tear excepted, on the completion of the work. E
The judge found that the Arbitrator had (1) misconstrued clause 25 (1) (b) of the
Agreement, and he held that the notice of termination given by the Corporation to
the Builders was bad, (2) that the Arbitrator did not adequately consider the Builders'
application for extension of time which was of vital importance and (3) the amount
awarded to the Corporation F was unwarranted. He found that the Arbitrator had
misconducted himself and he set aside the award and directed G
(a) The Builder's plant, equipment and tools be released forthwith to the
Builders.
(b) The award concerning compensation be set aside and will be the
subject of a new hearing. H
(c) The costs of the application be borne by the Corporation.
The Corporation appeals to this Court on two main grounds. Mr. Mkude for the
Corporation submitted that the judge I had erred in holding first, that the
Agreement had been unlawfully terminated
1986 TLR p176
MUSTAFA JA
A and secondly that the Arbitrator did not adequately consider the question of
extension of time.
On the issue of termination, the point turns on the construction of clause 25 (1) of the
Agreement. It reads:
B 25. (1) If the Contractor shall make default in any one or more of the
following respects, that is to say:
(a) if he without reasonable cause wholly suspends the carrying out of the
Works before completion thereof, or
C (b) if he fails to proceed regularly and diligently with the Works,or
(c) if he refuses or persistently neglects to comply with a written notice
from the Architect requiring him to remove defective work or improper materials or
goods and by such refusal or neglect the Works are materially affected, or D
(d) if he fails to comply with the provisions of clause 17 of these
Conditions,
E then the Architect may give to him a notice by registered post or recorded
delivery specifying the default, and if the Contractor either shall continue such
default for fourteen days after receipt of such notice or shall at any time thereafter
repeat such default (whether previously repeated or not), then the Employer without
prejudice to any other rights or remedies, may within ten days after such F
continuance or repetition by notice registered post or recorded delivery forthwith
terminate the Employment of the Contractor under this Contract, provided that such
notice shall not be given unreasonably or vexatiously ... G
The Arbitrator gave detailed reasons for his finding. As regards the notice of default,
he was satisfied that the default notice of 7th June, 1982 was reasonably issued, the
default being that the Builders failed to proceed regularly and H diligently with the
works.
The Arbitrator held that the default was repeated on 26th January, 1983 when, on a
site visit, it was discovered that the labour force had dropped from 49 to 12, and there
was no foreman on the site. And by a letter of 28th January, 1983, the Builders stated
that building on the site had stopped. The notice of termination was given on 4.2.83,
within 10 days I of the repetition of the default on
1986 TLR p177
MUSTAFA JA
A 26th January, 1983, and 28th January, 1983.
The judge was not satisfied as to when the Builders had repeated the default, which in
his view, was crucial, as the notice of termination had to be given within 10 days of
the repetition of the default.
B Mr. Lakha for the Builders submitted as follows: First even if the default notice of
7.6.82 was valid, he contended that the notice of termination of 4.2.83 was not made
within 10 days of the repetition of the default. He said that there could be no
continuance of the default the subject of the notice of 7.6.82, as there was an interval
of 8 months; and during such interval the Builders had done satisfactory work. There
could only be a repetition. It was not established that the default C discovered on
26th January, 1983 was repeated the first time that day. To be a repetition Mr. Lakha
contended that the default must have occurred the first time after a lapse of time. If
the occurrence had happened on an earlier date it would be continuation, not a
repetition. He emphasised that "continuance" and "repetition" are mutually exclusive,
a D continuation cannot be a repetition.
I am not persuaded by this argument, ingenious though it is. If after a default has
been established, and it has ceased or E has been remedied, a repetition of such
default occurs when it takes place again. It matters not when one becomes aware of
the default, whether on the first day it was repeated or on some subsequent date, so
long as the default F continues. A repetition of a default can have no exclusive
reference to the date of its first occurrence, it is repeated every time the default
occurs. The repetition of a default is the act of the default itself being repeated, and
once the default is repeated, then a notice of termination within 10 days of such
occurrence complies with the provisions of clause 25 (1) (b).
Mr. Lakha also contended that there was no or no sufficient evidence of the default
being repeated. The Arbitrator had G relied on two matters for his finding that the
default was repeated, (1) the site visit on 26.1.83 and (2) the Builders' letter of 28.1.83.
Mr. Lakha submitted that the site visit was referred to only in the final written
submission to the Arbitrator made by the Corporation and was not a matter given in
evidence. As regards the letter of the Builders Hdated 18.1.83 he submitted that the
sentence "the project has come to a standstill", should not be taken out of its context.
The Builders were complaining of the attitude and stance adopted by the Architect in
respect of the work done by the Builders. I
Mr. Mkude for the Corporation referred to the large number
1986 TLR p178
MUSTAFA JA
A of site visits made as mentioned in minutes in the record prepared for the
Arbitrator. These were not in dispute and in fact he stated there was evidence
adduced before the Arbitrator of such visits. The site visits, at that period, used to be
about once every week or ten days. The letter of 28.1.83 clearly established that the
work had come to a standstill. B
The Arbitrator was satisfied that the site visit of 26.1.83 did take place. There was
certainly evidence to support his finding. He construed the letter of 28.1.83 as
evidence that at that time the work on the site had stopped.
C On this point the judge stated that he was not satisfied as to when the Builders
repeated the default. In my opinion if he had properly directed his mind to the
Arbitrator's finding that such evidence was to be found in the site visit on D 26.1.83
when the labour force had fallen to 12 and the foreman was absent, as well as to the
admission in the Builder's Letter of 28.1.83 that work had come to a standstill, I think
he would have concluded that the default was repeated on 26.1.83 and 28.1.83. The
default, let me repeat, was failure to proceed regularly and diligently with the works".
The notice of termination was given on 4.2.83, within 10 days of the repetition of
such default in terms of Clause 25 (1) E (b) of the agreement.
On the issue of extension of time Mr. Lakha submitted that the Arbitrator had found
that the Builders had applied to the Architect for extension of time for 377 days. The
Arbitrator was of the view that the Builders were entitled to some at F least of those
days, and that there was an element of negligence on the part of the architect in
dealing with such application for extension of time. I am not at the present
concerned with another extension for 254 days which relates to the extra work
connected with the variation in the original Agreement. Mr. Lakha submitted that if
the Builders were G granted the full extension of time applied for, it could be found
that there was no undue delay by the Builders in carrying out their building work.
He went into figures and time frames and sought to establish that if the Builders had
obtained such full extension there would be no default. He contended that the
Arbitrator ought to have decided how much extra H time was due to the Builders, so
as to assess the progress of the work done, but the Arbitrator had failed to do so. He
submitted that this matter of extension of time should be remitted to the Arbitrator
for a fresh hearing. From Mr. Lakha's arithematical calculation he estimated that at
the time the Agreement was I
1986 TLR p179
MUSTAFA JA
A terminated about two thirds of the work in the original Agreement had been
completed.
Mr. Mkude, from his arithmetical calculation, claimed that by the time the agreement
was terminated, only one third of the work in the original Agreement was completed.
He maintained that in any event the default was basically concerned with B the
progress aspect of the work, that work had to be done "regularly and diligently". The
issue of when the work was to be completed has to be viewed in the context of the
progress of the work being carried out "regularly and diligently". The evidence, he
contended, established that work had come to a standstill on 18.1.83. The issue of
extension of time C was not of importance in the numerical context, but in the
context of the concept of proceeding with the work "regularly and diligently". He
admitted that there was no evidence based on quantities about the portion of work
completed when the Agreement was terminated. The estimates given were based on
the amounts of money paid and the balance remaining unpaid. D
On the question of extension of time the judge was of the view that it was of vital
importance and deserved a "deep and careful consideration". He thought that if the
Arbitrator had granted the full extension of time asked for by the Builders, E he
would have dismissed the Corporation's contention that he had committed the
default of failing "to proceed regularly and diligently with the works". The judge did
not hold that the claim for extension was well-founded, but he held that the F
Arbitrator did not adequately consider this issue. The judge however had held that
the notice of termination was bad on the ground that there was no evidence that a
repetition of the default had occurred within 10 days when the notice of termination
was given. He did not link this question of the extension of time directly with the
issue of the validity or otherwise of the notice of termination. G
The Arbitrator dealt in great detail in his award with the extension of time issue. He
dealt with it when considering the issue of extension of time proper and in
connection with the issue of the validity of the notice of termination of 4.2.83. He
considered the reasons for some of the extra time asked for as being due to lack of
materials, and he concluded that the H "conditions which existed during the
contract period as far as the availability of the said material is concerned, were not
different from those that existed in 1981, when the Contractor prepared his tender
bid". He went carefully into the arguments and submissions put forward by the
parties, and the Arbitrator devoted several pages in his award to this I matter.
1986 TLR p180
MUSTAFA JA
A The Arbitrator took into account all the relevant factors, and in arriving at his
conclusion he took note of the extension of time claimed by the Builders, the reasons
advanced by the Builders for the rate of progress and so on and so forth. The
Arbitrator was experienced in the matters in dispute between the parties, and he gave
sound reasons for his conclusion. I can find nothing that indicated that the Arbitrator
had misdirected himself or had gone wrong, and, for my B part, I am satisfied that
the Arbitrator was entitled, on the evidence before him, to have reached the
conclusion that despite the right of the Builders to some of the extra time he had
asked for, it would not have really mattered for it was C clear that the Builders had
failed to proceed regularly and diligently with the works. I do not agree with the
judge when he found that the Arbitrator did not adequately consider the Builders'
application for extension of time. In my view that point was adequately considered
by the Arbitrator. D
I now come to the matter of the monetary award made by the Arbitrator. The judge
found that the said award was unwarranted and directed that this issue be remitted to
the Arbitrator for a fresh hearing. I think the judge was right. The Arbitrator had
clearly erred in his assessment of the sum found due to the Corporation. He gave no
clear indication as to E how he had arrived at his figure. Mr. Lakha submitted, and
Mr. Mkude eventually agreed, that this matter be remitted for a fresh hearing.
In deciding this matter of the monetary award the Arbitrator should take into account
the following, among other, factors: F
(1) The Arbitrator had clearly found that the Builders' responsibility was
limited to about 25.5 million shillings (to the scope of works as defined in the original
Agreement)
G (2) The Builders had been paid about 12.8 million shillings for work done,
leaving a balance of about the same sum.
(3) The sum paid to the Builders includes some of the extra work as
contained in the variation to the original Agreement.
(4) An estimate has to be made as to when the works in the original
Agreement would be completed if they have not yet been completed. In this
connection, it must be kept in mind that, the new contractor would be erecting on
the basis of the H Agreement as varied including the extra work. Any extra time
due to the Builders has to be computed and taken into account. I
(5) If there is an element of inflation in connection with the
1986 TLR p181
MUSTAFA JA
A cost of the uncompleted work in the original Agreement, the escalation
due to inflation assessed at 15% as contained in page 145 of the record of appeal will
be of relevance.
(6) Whether liquidated damages at Shs.6,000/= per day of delay as
contained in Clause 22 of the Agreement is applicable.
B In connection with the Builders' plant, equipment and tools, the judge had
ordered them to be released by the Corporation to the Builders "forthwith", i.e. on the
date of his judgment, 21st September, 1985. The judge made that order probably on
the ground that the termination notice was invalid. That order of the judge cannot
now stand and I C would restore the order of the Arbitrator on this matter. In any
event the Arbitrator will have to fix a completion date in respect of the uncompleted
work involved in the original Agreement, either actual or notional. The return of
such plant and equipment would be related to such a date. D
In the final analysis, I would set aside the order and ruling of Mapigano, J., except for
his order that the award in respect of monetary compensation made by the Arbitrator
in his Award be set aside and be the subject of a fresh hearing.
I would restore the findings of the Arbitrator that the notice of default of 7.6.82 and
the notice of termination of 4.2.83 E were valid and legal. I also would restore the
order of the Arbitrator that the costs of the Arbitration before him be borne by the
Builders, as well as his order in respect of equipment and plant.
F In regard to the fresh hearing on the issue of the monetary award, I would order
that the matter be arbitrated by the same Arbitrator in terms of Section 14 of the
Arbitration Ordinance. He should file his award within 3 months of the date of the
order remitting the award. The Arbitrator should take note of the factors in regard to
the monetary award mentioned earlier in this judgment. G
In the result in my opinion, the appellant has succeeded to the extent as above stated.
I would award the appellant half the costs of this appeal. I would not certify for two
advocates. I would make no order in respect of the costs in the High Court.
As the other members of the Court agree, it is so ordered. H
Order accordingly.
1986 TLR p182
A
0 Comments
PLACE YOUR COMMENT HERE
WARNING: DO NOT USE ABUSIVE LANGUAGE BECAUSE IT IS AGAINST THE LAW.
THE COMMENTS OF OUR READERS IS NOT OUR RESPONSIBILITY.